HISTORY OF ROSE CITY YACHT CLUB

 

Rose City Yacht Club traces its beginnings to 1932, when 20 Portland boaters organized the Rose

City Cruising Club, with headquarters at the Staff Jennings marina on the Willamette River.

In February 1939, a group of 10 organized the club, naming it Rose City Yacht Club. A floating

Clubhouse was built and moored at Tomahawk Island and the membership grew to 35. With the

onset Of World War II, the membership voted to disband for the duration. The clubhouse was used

by the Coast Guard in wartime, and later sold to the new Columbia River Yacht Club.

 

After the war the club was reformed, and in 1948 the tug Defender was purchased and moored at

Columbia Moorage as a clubhouse. While remodeling was underway the tug sank at its mooring, but

Undaunted club members raised it and completed the job. Two years later the club was moved

down- stream to the Larry Knoll property at 73rd and Marine Drive. Soon after, the Defender sank

again – This time it was a total loss - and meetings were conducted thereafter at the CRYC

clubhouse.

 

In the meantime the RCYC do-it-yourself tradition became firmly established as members pitched in

and installed new walkways, wiring and a well water system. Early in 1953 work began on a new

Clubhouse financed by bonds sold to members and with all labor performed by the membership. As

The list of members passed 100, in 1956 the two walks of the moorage were extended 50 feet, and

300 additional feet of frontage were leased from the Port of Portland.

 

With proceeds of a new membership bond issue in 1957, work parties constructed two new walks,

doubling the club moorage capacity. A social highlight of the year was the first RCYC Commodore's

Ball. Another $6,000 bond issue was required in 1958 to dredge silted areas in the moorage.

In 1960 RCYC became affiliated with the Pacific International Yachting Association, and several

members participated in the first PIYA sponsored NorPac Sailing Race from the Columbia River

light-ship to Port Townsend. This year also saw completion of a new ramp from the lower parking lot

to the moorage.

 

The Columbus Day storm was the big news of 1962. Our clubhouse snapped its mooring chains and

set sail for Vancouver, catching up in midstream on the lower tip of Lemon Island sandpit. A tug

retrieved it with only slight damage.

 

In 1963 the club was free of debt, with all construction and dredging bonds redeemed. The moorage

was improved with the installation of a new water supply system and the grading and graveling of the

lower parking lot. Subsequent improvements included the installation of security fences with magi-

netic card locks at the walkway entrances, rewiring of the clubhouse, purchase of two new electric

galley stoves, and the construction and launching of a club workboat, the Rose Bud.

 

In 1966, following negotiations with the Port of Portland, RCYC undertook another major expan-

sion Program. The Knoll property was abandoned, and the club leapfrogged downriver, adding 370

Frontage feet to the 300 already under lease from the Port. The $40,000 project was completed in

1967, with financing provided by a $16,000 membership bond issue and the balance from the Port on

a nine- year lease-loan repayment agreement. RCYC's "New Look" featured five new, wider walks; a

new well; a new floodlighted parking moorage and a small boat dry storage float.

 

Another windstorm early in 1971 toppled several pilings, revealing wide spread dry rot. After a

thorough survey, 23 pilings were replaced in time to beat the spring freshet. Low water during 1973,

1974 and 1975 seriously hindered racing and cruising activity. Although dredging in 1976 restored a

minimum of eight foot depth throughout the moorage, a hydraulic study indicated the silting problem

was likely to continue indefinitely, and a search for a new location began.

 

Soon the Ed Hargrave moorage, about two miles downstream, was purchased. The property offered

Ready access to deep water in a good sailing area, 600 feet of waterfront and ample land space for a

parking lot and future clubhouse site.

 

A new moorage layout was designed and the entire area dredged to a minimum depth of eight feet.

About 13,000 cubic yards of spoil were deposited in the parking lot area, new piling driven, and a

new steel ramp constructed. A drainage system was installed in the parking lot, and protective rip-rap

placed on the bank. Cost of all improvements was raised through the sale of bonds to members.

Other than dredging, pile driving and parking lot construction, all work was performed by members

without pay. Members also contributed their time and their boats to the task of moving the clubhouse,

club walks and individual houses and slips to the new location. New plumbing and wiring were

installed, and the entire job completed in time for a celebration at the close of 1976.

During 1977 and 1978 a second steel ramp was constructed, flag pole erected and tee slips

constructed. Due to silting in, possibly from the Mt. St. Helens eruption and 1-205 bridge

construction, nearly 10,000 yards were dredged in 1982.

 

A new roof was put on the clubhouse, gas furnace was installed, and the galley rearranged with new

stove, dishwasher, microwave oven and water heater.

 

A contract to rebuild Walk #1 was awarded to Larson Marine Services. This was for the inshore half

and included new logs, stringers and decking. The project was completed in November and the cost

was $15,000.

 

In spring 1984 the remainder of Walk #1 was rebuilt and a wave barrier was added. The breakwater

walk was reinforced and the dolphins there were faced with protective metal pipe. The members

voted to spend $36,000 to design and install a new under walk electrical system with a hookup

between each two slips. The members also did much of the work.

 

The Property Development Committee gave a presentation to the membership on the building of a

shore side clubhouse, and at least 2/3 of the members voted their approval to pursue the issue, but it

was later voted down.

 

The First Mates organization went inactive at the end of 1984, to be replaced by a social activities

committee.

 

1985 was the year the boats needed wheels. Dredging was accomplished and boats back in place by

November. It was also the year the electrical installation was completed giving every slip an outlet and

no overhead wiring. A new water system was designed by member Ray Dougherty that was installed

in one day by the largest work party since the club moved.

 

The clubhouse has been improved with new tables and chairs, shutters and carpets in the section by

the galley. The galley was enlarged by 50% and made modern with new stoves, refrigerators,

microwave oven and countertops. The cabinets were modernized and a movable work table

provided. A large share of this work was done by members and The First Mates provided the new

equipment. The old warehouse was removed and the parking lot re-graveled.

 

1988 saw additional work on the clubhouse. Furniture was refurbished with new laminate on table-

tops, and new paint for both tables and chairs. The club jukebox was also replaced with a modern

stereo system. Silting in the moorage continued to be a problem, and after careful consideration of the

alternatives, the club purchased a dredge from the Portland Rowing Club. A cadre of operators was

trained, and by year's end Walks #4 and #5 had been dredged at a minimal cost. RCYC also

continued its cruising traditions, with record turnouts at the spring Sand Island and fall Beacon Rock Cruises.

 

1990 was the year of the sand. Our dredge put a 10' trench above Walk #1 to catch sand before it

reached the club. Walk #2 was dredged to -8' which is deeper than ever before. All this dredging

created quite a sand pile where the old warehouse used to stand.

 

The old pump house was removed. Lots of sand was moved to the banks and when they were

graded, grass was planted which has really improved the look of the grounds. New underground

wiring was installed in the parking lot along with some new lighting. As an alternative to our all wood

slips, a 38' fiberglass T-slip was built.

 

In 1991 RCYC continued to make major improvements to the moorage. A long range plan was

adopted calling for the replacement of our walkways with concrete walkways by 1998. The first 90

feet of concrete walkway was installed on Walk #2 with plans to replace all of Walk #2 and Walk #3

with concrete in 1992. The plan outlined capital improvements through the year 2005. The

membership also voted to begin planning a replacement clubhouse to be completed in 1997 or 1998.

 

Membership continued to grow and the moorage was full most of the year. With a full moorage the

financial strength of the club grew so that major improvements could be made without any special

assessments or dues increases.

 

1992 saw the beginning steps toward implementing the Long-Range Plan for club improvements. We

installed concrete walkways on Walks #2 and #3 and redecked and restrung the northern breakwater.

The club celebrated its sixtieth anniversary with a Gala Day Birthday Party on Opening Day at the

beginning of May.

 

December's mean easterlies and the fact that Salty's no longer provides any protection for Walk #1

resulted in damage to the inboard section of Walk #1. An assessment of the damage was made and

the Board brought this information to the club members at a general meeting where it was moved and

seconded to make the repairs with a concrete walkway. It is hoped to do this early in 1993.

1993 was a pivotal year for RCYC. We began with the need to replace Walk #1. After considerable

research the club voted to place itself in debt to the amount of $346,252 for 7-1/2 years to replace the

entire walk in concrete, supported by steel pilings. A contract was drawn up with a local firm –

Larson's Marine. This company could build us a structure with cast in place T-slips which would 

provide the moorage with the maximum protection from the occasional and predictive east winds.

Negotiations and permits delayed the beginning of construction to October, with completion

scheduled for February 1994.

 

The major event of 1993 was the burning of the mortgage - and this was done in true RCYC fash-

ion. It certainly was quite a party, with German sausages, Scottish bagpipes, the clubhouse filled to

capacity with happy people and a Fire Marshall to oversee the actual burning.

 

The clubhouse was finally hooked into a new sewer line through a unique, one design, floating tank

and a donated electric panel. An oil collecting container was built and installed in the parking lot. By

Laws changes were made to: reduce the Board size from 11 to 9 by combining the positions of

Secretary and Treasurer and reducing the number of directors by 1 and to change our procedures for

accepting new members. The membership voted in a $35/quarter increase in our capital improvement

assessment as well as increasing the amount new members must put into their refundable bond to

$500

 

1994 was a banner year for the club seeing the complete replacement of Walk #1 with new steel pil-

ings and the installation of our concrete walk featuring cast in place T-slips. The whole operation was

supervised by many "rail-birds" and the front of the clubhouse was the best seat on the river. By mid-

summer the new electrical and water systems were in place and boats were again shuffled to put the

moorage back in order. All was thought to be well, but Mother Nature had other ideas. The first

strong winter east winds caused some hinge and pile-hoop damage which required some rethinking

and repair.

 

On the social side of things RCYC enjoyed some record turnouts for cruises and functions. One of

the highlights of the year was our support and sponsorship of a fund raising event for "Team

Portland" –the racing yachts "Rage", "Sting" and "Magic Carpet" entered in the 1995 Pacific Cup

race to Hawaii. Over 300 supporters showed up maxing out the clubhouse to say the least. Over

$4,500 was raised and all three boats did super in the race. "Rage" set a new course record.

 

1995 - What a year!! It started with high winds from the east that damaged Walk #1 and ended with

high winds from the south that toppled 10 piling.

 

On the business side, the major topic of year was Walk #1. After outside engineers looked over the

walk and reviewed its design, it was determined that the structure was under-designed and would not

stand up to the wind and wave force present at that location. The club started legal action against the

contractors and this issue remained unresolved at the end of the year.

 

Because of the legal expenses and uncertainty regarding Walk # 1, the club had postponed replacing

25 older wood piling in the moorage until 1996. A December wind storm, which topped 10 piling

changed those plans. The membership voted to assess all active members $300 to cover the cost of

replacing all 25 piling.

 

A new storage shed/shower was built and a major remodel of the men's head in the clubhouse was

started with the moving of the hot water heater and furnace to the attic area.

 

On the social side the membership voted in an "Activities Fee" which would cover the cost of most

club events which were well attended. All the club cruises saw large turnouts (over 30 boats on Lazy

Days) and great weather (over 90 degrees on Memorial Day).

 

The moorage remains full and a waiting list of up to a year was faced by those wanting moorage.

1996 was the year we resolved many uncompleted projects and unfinished issues. But first, we had

to withstand yet another weather related emergency. The Commodore's Ball was postponed due to

severe icing and for the next week many members lives were put on hold as they struggled around the

clock to save the moorage from flood related damage. Fortunately, it got better from there.

 

We hosted Opening Day the first weekend in May at Hayden Island Yacht Club - we weren't yet

ready for visitors. The Luau came back and Oktoberfest was better than ever. But it seemed

somehow that mostly we worked.

 

The piling were replaced. The stringers under the clubhouse were fixed to eliminate the buoyancy

problems. The Walk #1 arbitration preparation continued as Walk #1 itself disintegrated further.

Musical boats was the name of the game as we labored to keep as many members in the moorage as

possible. Then, finally things fell in place. Walk #4's ultimate replacement was acquired early to use

temporarily on Walk #1. The members voted for a $150,000 E bond issue to fund the project. Just as

that installation began, the arbitration was settled with a check. By the end of the year, temporary

Walk # 1was in place and, with it, came the prospects of a full moorage.

 

1997 was the year when the weather finally treated us more gently. During the year we had a lot of

fun, we borrowed and spent a lot of money, and we made some major property improvements in our

facilities. All of Rose City's traditional cruises, social events, and other activities continued during the

year as members enjoyed good weather and having good times on and near the river.

 

Progress was made on major projects and many smaller ones. A contract for a replacement of Walk

#1, to be built by Bellingham Marine, was signed during the fall of 1997, bringing the long standing

issue of replacing Walk #1 close to a final conclusion. After reviewing all project financing options,

the traditional RCYC financing method of internal bond sales was combined with a bank loan to

obtain the funds to pay for the new walk. Existing D and E series bonds were refunded and new F

series bonds were sold. Installation of the new Walk #1 will take place in early 1998. During the low

water in the fall, rip rap was placed on the eastern part of the river bank to prevent further erosion.

Increasing costs finally caught up with us, forcing a modest increase in moorage rates, the first in nine

years.

 

1998 - In the spring we cut the ribbon on the replacement of the concrete Walk #1 dock and a new

concrete Walk #4 dock - a $650,000 investment. We are in debt again, and this time we even let a

bank in on it. Many members chipped in with a lot of labor and part of the financing for the venture.

The new docks significantly increased our overall worth and the tax person is significantly increasing

his take. For this reason moorage rates had to be raised a bit, but two-thirds of our dockage is now

concrete.

 

This was also the year of either a higher river bottom or lower water for longer than usual. But thanks

to a hard working and inventive dredge crew, we came out in good shape with a much improved

dredge and a big pile of sand. Also this year saw the initiation of a cruise to Victoria, and sad to say,

the last Oktoberfest.

 

1999 was the year of the "quarterdores" as our Vice Commodore reluctantly resigned because of

family health problems. The Nominating Committee tapped 4 previous commodores (John Dees,

Lynn Easton, Ron Moran and Jack Mitchem) for the privilege of leading the club through the year.

 

Our popular educational program included a revised kid’s day on boating safety. Dredging continued

to be an issue and the Board elected to convert the existing dredge to hydraulics and generally

upgrade it for continuing service. The alternative - a new dredge - was a little out of reach financially.

 

The uneventful rollover to the year 2000 was celebrated by a smashing New Year's Eve party.

2000 - Is it the first year of a new century or the last year of the old century? No matter, RCYC just

keeps rolling along, and getting better and better. The year was kind to us weather wise: no storms,

no floods, no problems.

 

The big news all year was "The Dredge"! We kept the dredge busy moving sand out of the moor- age

by starting early and working right up to the end of our seasonal permit period. Our good 01' dredge

did the job with greatly improved efficiency due to our investment in, and hands on completion of,

the second phase of our dredge modernization and improvement program. A few of the major items

included a new main pump, new gantry, rebuilt and enlarged house, new hydraulically driven primer

pump and other improvements to the hydraulic systems. Boy, did we move a lot of sand! All the

fairways were dredged to design depths. We even dredged some slips that were in desperate need of

more water. A new topographic feature arose in the parking lot that many were calling "Mt. Rose" (a

few feet higher and we would have had to place an aircraft warning beacon on its summit!). Thanks to

a serendipitous arrangement with a local contractor, the dredge pond was dug out several times

during the season. This same contractor will also remove the massive pile of sand during the off

season at no cost to RCYC.

 

2000 was also a year for rebuilding RCYC membership. The year started with too many empty slips

and the realization that membership was declining. By years end, the moorage was full, and we have

many new members and new friends. We hosted an open house and invited prospective new

members to our new social event, the RCYC "Ice Cream Social". This new event and recruiting tool

worked very well for us.

 

The year was not entirely devoted to dredging and membership. We also initiated a small scale,

incremental program of moorage improvements. We ordered small quantities of concrete "fingers"

from Bellingham Marine for spring and fall delivery. The new fingers were used to replace old and

failing wood tee slips. All installation work was done by members, and included the refitting of walk

2 to provide adequate space between boats. This incremental approach to moorage improvement was

so successful that it is being carried forward to 2001 and beyond.

 

2001 at RCYC began well. The dredge was pumping, and a full crew was scheduled. RCYC publi-

cations came into the 21 century as the yearbook was converted to a professional digital format and

the Foghorn was available on the Internet. Electrical rates were changed to a specific rate by walk,

based on the actual history of each walk, to be updated annually. We got through the winter and spring

without floods or storms. the year looked like smooth sailing, but the river had other ideas. In mid-

July the river level dropped, the Headwalk was aground, and our floating shower/storage building

capsized. a midnight crew rescued much of the supplies and equipment, but our RCYC sustained

losses. Low water was grounding the Headwalk twice daily through July and August, causing

structural damage. We secured a permit and did some emergency dredging under the inboard end of

Walk 1, to protect it from further damage. A "Headwalk Reconfiguration Committee" was formed to

develop a remedy. The project would clearly involve the Headwalk, the bank, and some more

dredging. Construction was proposed for 2002.

 

Low water and broken docks did not prevent RCYC from sailing and cruising. The annual Lazy Days

cruise was well attended and appropriately disorganized. RCYC boats did very well in the Oregon

Offshore. Membership was a bright note, with new members joining almost every month. 2001 saw

the first volunteer organized river beach clean up. RCYC represented itself well, providing two

workboats and skippers along with club volunteers.

 

The year ended with the dredge pumping, and a full crew scheduled. There was a lot of talk about

Headwalk design, and a continued interest in community involvement and service.

2002 was the "Year of the Headwalk". The Club undertook the project that would see the replace-

ment of the old wooden headwalk, which through time and damage from the low water of 2001 was

nearing the end of its useful life. This was one of the most complex construction projects in the histo-

ry of RCYC. Several members with expertise in planning, finance, and construction stepped forward

to oversee the various phases of the $350,000 project through to successful completion.

 

To allow for excavation and placement of additional riprap, the shop, dinghy floats, and clubhouse

were temporarily relocated. The old headwalk was cut into sections and removed. The river bank was

excavated and new riprap was placed to protect the new slope. After placement of the riprap, the new

sections of head walk were installed and the walkways were reconnected. Simultaneously, the

electrical distribution panels were totally updated and upgraded. Through all the mayhem, only one

club meeting had to be held elsewhere. At the end of the year, after two months of construction, the

new headwalk was in place, complete with electricity.

 

With the completion of dredging early in the year, all fairways and nearly all slips were brought to

their design depths. This resulted in yet another pile of sand in the parking lot, but it was gone by the

time the head walk project started.

 

Thanks to this effort, the loss of half the dredging window late in the year due to the headwalk work

was of no consequence. 

 

2003 was a quiet year at RCYC. A mild winter spared us calamitous events within the moorage and we 

were able to concentrate our efforts and energies on social events, cruising  and making the grounds and 

clubhouse more presentable. Committees were established to plan the remodeling on the club house; to 

establish a plan for the storage, showers and dredge floots; and to plan for the cleanup of the parking lot 

and grounds. By the year end the lot committee had executed one of their plans; the terracing of the south 

bank, simplifying grounds upkeep. the floats and storage committee had proposed a plan for a float that 

would support the dredge, the shop. the showers and some storage and were collecting data for its design; 

and the club house committee had established a plan for the inside of the club house, and most of the 

cabinetry was completed. The actual remodel wouldn't begin until February 2004.

Dredging went well until a hole was worn in the pump casing. A repair was effected and the dredge was in 

operation again in about a week.

2004 came in like a lion.  We started the year with an ice and snowstorm, which left the moorage without water.  The 

resident members lived on bottled water for nearly a week.  The soup and sail was postponed because of the weather.  The 

only benefit from the storm was we now know where the weaknesses are/were in the water system.  They have been 

fixed.  

In February, the clubhouse was gutted and a dedicated group of folks spent an unlimited amount of time remolding the 

building.  The finished product was well worth their effort and now enjoyed by everyone.  By spring the work parties had 

the grounds cleaned up, the junk disappeared, the grass was mowed and the place looked like a yacht club once again.  

With Opening Day came the start of the sailing season with all that it implies.  An assortment of cruises, special events and 

walk parties were executed.  Grass was planted on the south side of the parking lot.  One more step completed in the 

beautification of the property.  The establishment of a home for the dredge developed into a full-blown Walk 5 

replacement and a shower, storage and dredge float. Opps! The dolphins securing the Breakwater are pulling out.  The 

increased river traffic has not been kind to them.  An emergency replacement project was started with the necessary 

permits obtained with the final completion being accomplished within the “in the water work window”.  Walk 5 is now on 

hold.  2004 was a year of hard work and cooperation by the members who can now reap the rewards of their efforts.

2005 began with an emergency project at the club.  The wooden pilings holding the club breakwater in place began showing signs

of failure last summer.  The engineering report received in late December confirmed the need to replace the pilings.  While the

permit process was underway, contracts were written and signed with Hickey Marine.  Permits were received on February 8, and

work began February 11.  The last piling was installed on February 14, thus providing a great Valentine’s day present for the Club. 

Fastening the piling to the breakwater was completed by March 31.

RCYC was the host club for Opening Day this year.  Spring work parties were spent preparing the facilities for this event.  RCYC 

sparkled like the gem we all know her to be.  The ceremonies and parade were held under cloudy, but rainless, skies.  The 

Daughters of Neptune and Sea Scouts presented the colors and hoisted the burgees.  And, the “mountain” of hors d’houvres 

served to guests after the parading of the fleet was truly impressive.

The fall began with the resumption of work parties to prepare the club for the winter.  The Walk 5 Planning Committee began 

meeting to plan the layout and obtain estimates of costs for putting in Walk 5 so that the Long Range Planning Committee could 

project when this could be accomplished.  And, for the first time in many years, there is no dredging to be done.  This has 

prompted some members of the dredging crew to suffer withdrawal symptoms.  However, the dredge has been keeping us busy in 

another way.  We have begun the process to obtain the next 5-year permit.  So far, the process is creating substantially more 

work for those involved.  In expectation of the significant higher costs, the membership approved a one-year increase in the 

dredge fees.

And lastly, the year roared out.  December saw an ice storm, several days of high wind and lots of rain.  However, all the work in 

the moorage has paid off with little damage reported
. 

 

 

 

 


Home / Foghorn / Calendar / Photos / Officers / Ship's Store / Racing / Links

Special Announcements / Membership / History / Year Book Advertisers / Reciprocals